< Back to News

FROM WORKSHOP TO SITE

SEPTEMBER 2020

From Workshop to Site

At Millimetre’s workshop in Brighton, a tremendous steel skeleton has been rapidly emerging. It will form the delicate superstructure of a garden pavilion-cum-guesthouse destined for the Isle of Wight. In the main hangar, a healthy collection of gently oxidizing off-the-shelf steel sections and staggeringly sharp, bespoke milled elements is set back from a row of socially-distanced workspaces. Millimetre’s metal workers have been working around the clock (and in the excessive summer heat) to cut, weld and grind the heap in front of them into the many precise modular components that will form the pavilion’s columns, floor and roof. An assembly line has been formed to increase the efficiency of fabrication, with a station each for repetitive rotary welding tasks, rotary grinding, welding using custom jigs and more complicated non-linear welds. As the steel passes through the workshop, glistening segments come to form elaborate sculptures. Adjacent to the metalworking bays is a six-axis robot arm programmed to cut high density foam into jigs for the most intricate welding alignments. This will be essential to the success of the central roof truss node, where nine tubular sections converge. More on this will follow at a later date.

The pavilion will be lifted off the ground by cantilevering trusses held from the main columns, which are formed of four tubular sections tied together by intermittent thin plates along their height. The lower portions of these columns, which sit beneath the floor build-up, are amicably referred to as the daleks. These stub columns are the first pieces to be finalized, quickly assembled in tandem to confirm tolerances, and sent away to be painted for corrosion protection before arriving to site.

On the northeast coast of the Isle of Wight, the site falls to overlook a protected marshland with tidal flows fed by the Solent. A shallow depression with raking banks at the bottom of the hill will conceal the feet of the pavilion superstructure; the baseplates of the stub columns now erected atop the long strip foundations and adjoined to form the triangulated support for the floor and deck above. Located to capture rainwater dropping from the overhanging roof eaves, the perimeter gravel drain will also mark the boundary between building and landscape, with tall, wild grasses merging with the wetland beyond..

As the pavilion envelope will be formed largely of full-width glass spans closely abutting the columns, erecting the steel frame precisely is critical. Despite a remarkable installation tolerance of +/- 3mm diagonally across each 5 x 5m bay, the stub columns must be shimmed to ensure exact alignment and verticality. Between them, the galvanised (and thus silvery) internal floor beams are distinguishable from the external floor beams, which are coated to resist corrosion and painted to achieve a warm metallic finish. With the cantilevering terrace beams installed additionally, a datum is formed approximately 180mm below the intended finished floor level from which the remainder of the pavilion will rise..

Back in Brighton, the columns which will stand on the shoulders of the stubs now installed on site are laid out one by one. Their height and slenderness astound – a true feat for the structural engineers, Smith & Wallwork. It is through, not around these columns that the thermal envelope will run, with tall and narrow glazing centred on each column between the four vertical tubes. The next test-build will involve hoisting up these columns, narrowly missing the suspended lights of the workshop, to bolt on the roof trusses via the halving joints rigidly reaching out to receive them. That dramatic and exciting update will have to follow.

LARGE-SCALE MODEL MAKING

SEPTEMBER 2014

The use of physical models by architects is well established, and can be seen throughout history as the natural partner to drawings for exhibiting a proposal of the building prior to construction. Within our practice, models are rarely produced as mere presentation pieces, but rather as tools for exploration. This role makes them less precious and complete, with the ability to change and adapt the design following the feedback that the model has initiated.

The type of models that I enjoy most are those of a larger scale, of 1:20 and above where you are able to get your head inside and truly appreciate the space. In addition to the final form of such models, much is learnt through the process of construction. Structure, surfaces and junctions are some of the issues that require resolution during the making of the model. Within our studio space, we have a large area dedicated to model making, which allows for building and display of sizeable pieces.

Large Scael Model

During our work on a new build private residence in Hampshire, we carried out much of the design work on the external envelope through the use of physical models. They were worked up in increasing scales including a 1:10 piece of the facade. In particular, we were considering the form of the heavy external piers, fascias and cornices against the lighter timber elements that sat within them. We made the model using a similar sequence to the proposed building construction. We put the more solid facade elements in place so that we could begin considering a number of different forms for the timber window framing that sat within. The glazing was again produced in a similar method to the full-scale building, with a timber-framed bay built separately prior to installation in to the existing facade. We fixed these delicately so that removal would be possible.

We worked on a number of iterations of the window form, adapting the frames and constructing new versions when modification was not possible. Each time, the model was left on display within the studio so that everyone in the practice could consider the alternative versions and provide feedback. Once we had a favoured form, we used the same model to illustrate the proposal to the clients for approval.

I believe that such iterative assessments and amendments would only have been possible through the use of a large-scale physical model. Building models is about constructing space, and many of the activities are similar in technique and execution as the construction of a real building. By carrying out these actions in miniature we may appreciate the building as a physical form and understand the three dimensional mass. Building of models is our primary opportunity to test and refine our building form, whilst experiencing and discovering an approximation of the processes that will be required to make it.

Alastair Crockett studied at the University of Bath, University College London and London Metropolitan University. Since joining Niall McLaughlin Architects in 2012 he has worked on the T1 building in King’s Cross; a private residence in Hampshire and the Nazrin Shah Building for Worcester College in Oxford.