BALLIOL COLLEGE, SPORTS PAVILION

NOVEMBER 2019

Balliol College, Sports Pavilion

7:45 AM, London Bridge. The train from Uckfield just entered the station and is spitting out hundreds of commuters, flowing past us. We hop on the now empty train and leave London to visit our timber sub-contractor’s workshop in East Sussex.

We are fast approaching the construction stage of our Sports Pavilion project for Balliol College in Oxford and were invited to review a mock-up of the roof structure. The pavilion roof is formed of slender sweet chestnut glulam joists; 10 layers are stacked on top of each other, each layer cantilevering further into the space, creating a coffer.

1:50 model

From outside the roof structure expresses itself as a lantern, popping up in the centre of the building. The lantern is fully glazed, allowing for rays of sunshine to enter through the stacked glulam. In the evening, the dense timber lattice will be highlighted by a subtle glow, originating from LED strips, that are recessed in the top of the glulam joists.

The mock-up in Inwood’s (timber sub-contractor) workshop

Lighting strategy detail plan and section

The mock-up was used to test the connection details between the individual layers of glulam, the construction sequence, and the integration of the LED strips and the associated wiring. Preceding the assembly of this mock-up, these details have been worked through and coordinated in many lengthy design workshops, involving the contractor, structural and electrical engineers, the timber sub-contractor, electricians and us architects. As such, it was even more enjoyable to review the mock-up with all the parties involved and to see our combined efforts bearing fruit.

The carpenters who built the mock-up and the Electrical Engineer, Design Manager, and Architect discussing the installation and accessibility of the LED strips

AUCKLAND CASTLE PLANNING APPROVAL

MARCH 2015

Auckland Castle Planning Approval

We have received planning approval and Listed Building Consent for the restoration and extension to Auckland Castle in Co. Durham. The project involves repairs and alterations to the existing listed buildings, a new museum extension and a visitor reception building facing the town square. Given the high sensitivity of this unique site, the planning process took almost one year, involving a very constructive dialogue with English Heritage and Durham County Council. The designs had overwhelming support from local people.